Please give your comments regarding to the drawing

[复制链接]
发表于 2012-6-21 09:38 | 显示全部楼层 |阅读模式 来自: 中国上海
题干
52.jpg -->
A ship was built on 2005-02-01 and the oily water separator system was arranged as the drawing. Please give your comments regarding to the drawing
A
B
C
D
E
答案
1 The ows bypass pipe to be dismantled
2 the re-circulating lines missing in the diagram. It should be after and adjacent to the overboard outlet of the stopping device to enable testing of the system. The re-circulating facility should be so configured as to prevent, under all operating conditi***, any by-pass of the oily-water-separator. Hopper arrangement to be used as per MEPC.107(49).
依据
(出处)
MEPC.107(49).