查看: 3437|回复: 12
收起左侧

[问题已经解决] 电缆通舱件的安装,需要报船检吗?

[复制链接]
发表于 2008-5-13 16:15 | 显示全部楼层 |阅读模式 来自: 中国浙江温州
电缆通舱件的安装,需要报船检吗?
回复

使用道具 举报

龙船学院
发表于 2008-5-13 16:23 | 显示全部楼层 来自: 中国浙江台州
跟这学学,顺便问下,其他地如穿舱管用报么??
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:27 | 显示全部楼层 来自: 中国山东青岛
需要
截取一段DNV规范,证明是需要船检看的
C 300 Penetrations of bulkhead and decks
301 General
a) Penetrations of watertight bulkheads and decks shall be
carried out either with a separate gland for each cable, or
with boxes or pipes filled with a suitable flame retardant
packing or moulded material, in order to ensure the integrity
of the watertightness of the bulkhead or deck. The installation
shall be in accordance with the manufacturers'
installation instructions.
b) Fire rated penetrations shall be documented as required by
Pt.4 Ch.10 ((Rules for Classification of Ships)).
Guidance note:
Penetrations of watertight bulkheads should be placed as high as
practicable.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
302 Thermal insulation
Cable runs shall not be laid in or covered with thermal insulation
(e.g. through refrigerated cargo holds), but may cross
through such insulation.
303 Hot oil pipes near to penetrations
The distance from cable penetrations to flanges of steam or hot
oil pipes shall not be less than 300 mm for steam or hot oil
pipes with diameter D ≤ 75 mm, and not less than 450 mm for
larger pipes.
304 Chafing
Penetrations of bulkheads and decks shall be such that the cables
are not chafed. (Interpretation of SOLAS Ch. II-1/45.5.5)
305 Mechanical support of penetrations
The cable shall have mechanical fixing on both sides of a bulkhead
penetration.
C 400 Fire protection measures
401 General
The cable installation shall be protected against fire, fire
spreading, thermal, mechanical, corrosive and strain damage.
(Interpretation of SOLAS Ch. II-1/45.5.2)
402 Flammable materials
Cables shall not be installed in contact with flammable materials
such as wooden bulkheads, when the conductor temperature
exceeds 95°C at full load, at the actual ambient
temperature.
403 Precautions against fire spreading in cable bunches
Cables that are installed in bunches shall have been tested in
accordance with a recognised fire test for cables installed in
bunches, such as the test specified in IEC 60332-3, or be provided
with protection according to 404.
Guidance note:
A cable bunch in this context is defined as five or more cables
laid close together in trunks from machinery spaces and in spaces
with a high risk of fire, and more than 10 cables in other areas.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
404 Cable bunches not complying with IEC 60332-3 or other
recognised standard fire spread test.
a) Cable bunches, not complying with flame retardant properties
according to IEC 60332-3, shall be provided with
fire stops having at least class B-0 penetration properties
at the following locations:
— cable entries at the main and emergency switchboards
— where cables enter engine control rooms
— cable entries at centralised control panels for propulsion
machinery and essential auxiliaries
— at each end of totally enclosed cable trunks.
Additional fire stops need not be fitted inside totally enclosed
cable trunks.
b) In enclosed and semi-enclosed spaces, cable runs not complying
with flame retardant properties according to IEC
60332-3, shall be provided with fire stops having at least
B-0 penetrations:
— at every second deck or approximately 6 metres for
vertical runs
— at every 14 metres for horizontal.
Rules for Ships / High Speed, Light Craft and Naval Surface Craft, January 2008
Pt.4 Ch.8 Sec.10 – Page 67
DET NORSKE VERITAS
Alternatively, to additional fire stops, fire protective coating
may be applied to the cable bunch according to the following:
— to the entire length of vertical runs
— to at least 1 m in every 14 m for horizontal runs.
405 Fire resistance of penetrations
Where "A" or "B" class bulkheads or decks are penetrated for
the passage of electrical cables, arrangements shall be made to
ensure that the fire resistance of the bulkheads or decks, is not
impaired.
Guidance note:
Cable transits in "A", "B" or "F" class divisions should not have
more than 40% of the inside cross sectional area of the transit occupied
by cables. The installation should be in accordance with
the transit manufacturer's instructions.
---e-n-d---of---G-u-i-d-a-n-c-e---n-o-t-e---
406 Fire resistant cables
For requirements for fire resistant cable, see Sec.2 J102.

这段是专门针对电缆管过舱件的

[ 本帖最后由 alphasen 于 2008-5-13 16:29 编辑 ]

评分

参与人数 1 +2 金币 +4 收起 理由
supervision + 2 + 4 感谢回复

查看全部评分

回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:29 | 显示全部楼层 来自: 中国浙江台州
晕死,这么长,还是E问。!!慢慢研究!!
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:30 | 显示全部楼层 来自: 中国山东青岛
哦,我只是想 证明确实需要船检看而已,内容仅供参考,呵呵
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:30 | 显示全部楼层 来自: 中国浙江台州
对了,是不是应该先做货舱内管路地气密,再做货舱气密!!
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:31 | 显示全部楼层 来自: 中国浙江台州
呵呵,不过还是谢谢啊!!
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:37 | 显示全部楼层 来自: 中国山东青岛
,你觉得呢?
最好按你的顺序,否则如果管路泄露就是 货舱气密失败,然后再 漫无目的的找哪个地方漏了,找了3天,哦,管子漏了,再修理管子,然后再管路气密,然后再做一变货舱气密。。晕了
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:40 | 显示全部楼层 来自: 中国浙江温州
原帖由 alphasen 于 2008-5-13 16:37 发表
,你觉得呢?
最好按你的顺序,否则如果管路泄露就是 货舱气密失败,然后再 漫无目的的找哪个地方漏了,找了3天,哦,管子漏了,再修理管子,然后再管路气密,然后再做一变货舱气密。。晕了



先给你自己做个气密!!!

评分

参与人数 1金币 -2 收起 理由
supervision -2 这里不可以这样灌水

查看全部评分

回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:42 | 显示全部楼层 来自: 中国山东青岛
   不敢了
回复 支持 反对

使用道具 举报

发表于 2008-5-13 16:43 | 显示全部楼层 来自: 中国浙江台州
呵呵,因为我以前做地一条船就是没写协调好,穿舱管还没烧焊,就做气密,还好是前一天晚上把气打进去了,还没来得急报就没压了!!
回复 支持 反对

使用道具 举报

发表于 2008-5-20 10:19 | 显示全部楼层 来自: 中国河北秦皇岛
穿水密舱壁、穿防火分割的电缆件,应该报验吧。
回复 支持 反对

使用道具 举报

发表于 2008-5-28 21:39 | 显示全部楼层 来自: 中国江苏南京
自检合格后还怕报检吗?通舱件的安装是有一定规范的.
回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册