查看: 2053|回复: 3
收起左侧

Frontline 取消与荣盛,金海湾订单若干

[复制链接]
发表于 2009-5-31 20:34 | 显示全部楼层 |阅读模式 来自: 新加坡
据5月30日www.motorship.com消息,Frontline取消两艘VLCC和四艘苏伊士,以下是全文:
Frontline cancels six tankers
Date: 30 May 2009                                                                                                                                | back
JohnFredriksen's Frontline has cancelled orders for six newbuilding verylarge crude carriers and Suezmaxes at Chinese shipyards worth more than$550m and representing 33% of its order-book. However, Jens MartinJensen, now Frontline Management's permanent chief executive, saidFrontline did not expect to cancel further newbuilding contracts. Afterthe company's first quarter results were issued, Jensen predicted thata third of all tanker orders could be delayed or cancelled.

Hetold a conference call that some vessels due for delivery in the fourthquarter of this year could be pushed back into 2010. However, he saidit would be from the middle of next year and into 2011 and 2012 werethe market would "see the big change in the orderbook."

Frontlinesaid it had agreed with Jiangsu Rongsheng Heavy Industries and ZoushanJinhaiwan on the cancellation of four Suezmaxes and a pair of VLCCsrepresenting a contractual cost of $556m. The company had a total of 18newbuildings on order with eight Suezmaxes contracted at JiangsuRongsheng Heavy Industries, four VLCCs at Shanghai WaigaoqiaoShipbuilding, and six VLCCs on order at Zhoushan Jinhaiwan Shipyard.

"Theinstalments already paid on the cancelled newbuildings will be appliedto and set off against future payments on the remaining newbuildings,"Frontline said. Jensen said Frontline was not paying any penaltycharges for the cancellations. In the case of the Suezmaxes atRongsheng, for example, the newbuildings were running behind schedule.Frontline had agreed to defer the delivery of the first four vessels inreturn for cancellation of the last four ships. The four Suezmaxes areexpected to be seven-to-nine months later than originally scheduled.

Jensensaid he did not expect any more cancellations in Frontline's order-bookalthough if there were more delays "you can never say never".Frontline's newbuilding programme now comprises four Suezmaxes andseven VLCCs worth $1.1bn.
回复

使用道具 举报

龙船学院
 楼主| 发表于 2009-5-31 20:36 | 显示全部楼层 来自: 新加坡
晕,怎么会这样
Frontline cancels six tankers

John Fredriksen's Frontline has cancelled orders for six newbuilding very large crude carriers and Suezmaxes at Chinese shipyards worth more than $550m and representing 33% of its order-book. However, Jens Martin Jensen, now Frontline Management's permanent chief executive, said Frontline did not expect to cancel further newbuilding contracts. After the company's first quarter results were issued, Jensen predicted that a third of all tanker orders could be delayed or cancelled.

He told a conference call that some vessels due for delivery in the fourth quarter of this year could be pushed back into 2010. However, he said it would be from the middle of next year and into 2011 and 2012 were the market would "see the big change in the orderbook."

Frontline said it had agreed with Jiangsu Rongsheng Heavy Industries and Zoushan Jinhaiwan on the cancellation of four Suezmaxes and a pair of VLCCs representing a contractual cost of $556m. The company had a total of 18 newbuildings on order with eight Suezmaxes contracted at Jiangsu Rongsheng Heavy Industries, four VLCCs at Shanghai Waigaoqiao Shipbuilding, and six VLCCs on order at Zhoushan Jinhaiwan Shipyard.

"The instalments already paid on the cancelled newbuildings will be applied to and set off against future payments on the remaining newbuildings," Frontline said. Jensen said Frontline was not paying any penalty charges for the cancellations. In the case of the Suezmaxes at Rongsheng, for example, the newbuildings were running behind schedule. Frontline had agreed to defer the delivery of the first four vessels in return for cancellation of the last four ships. The four Suezmaxes are expected to be seven-to-nine months later than originally scheduled.

Jensen said he did not expect any more cancellations in Frontline's order-book although if there were more delays "you can never say never". Frontline's newbuilding programme now comprises four Suezmaxes and seven VLCCs worth $1.1bn.
回复 支持 反对

使用道具 举报

发表于 2009-5-31 20:41 | 显示全部楼层 来自: 中国江苏泰州
接下来的日子里,这种现象将会屡见不鲜地
回复 支持 反对

使用道具 举报

发表于 2009-5-31 20:57 | 显示全部楼层 来自: 中国江苏南通
不会吧
我怎么一点不知道呀
回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

小黑屋|标签|免责声明|龙船社区

GMT+8, 2024-11-15 17:31

Powered by Imarine

Copyright © 2006, 龙船社区

快速回复 返回顶部 返回列表