如题,管理计划应该很快就要生效了,生效后,关于强制实施的时间是怎么理解的?
Regulation B-3 - Ballast Water Management for Ships
1. A ship constructed before 2009:
.1. with a Ballast Water Capacity of between 1500 and 5000 cubic metres, inclusive, shall conduct Ballast Water Management that at least meets the standard described in regulation D-1 or regulation D-2 until 2014, after which time it shall at least meet the standard described in regulation D-2;
.2. with a Ballast Water Capacity of less than 1500 or greater than 5000 cubic metres shall conduct Ballast Water Management that at least meets the standard described in regulation D-1 or regulation D-2 until 2016, after which time it shall at least meet the standard described in regulation D-2.
2. A ship to which paragraph 1 applies shall comply with paragraph 1 not later than the first intermediate or renewal survey, whichever occurs first, after the anniversary date of delivery of the ship in the year of compliance with the standard applicable to the ship.
比如,2011年 keel laid, 2012年5月交船,》5000M3,对于第2条,那么是不,2016年5月后的第一个中检/特检,开始安装??
如果是2011年keel laid, 2016年5月交船呢?》5000M3, 那么是不是 指交船的时间可以不安装,但是交船后第一次坞检再改 也来得及呢??
请高人指点!!!! |
|