Single Generator Operation
Where the electrical power is normally supplied by a single generator, provision is to be made upon loss of power for automatic starting and connecting to the main switchboard of a standby
generator(s) of sufficient capacity with automatic restarting of the essential auxiliaries in sequential
operation, if necessary, to permit propulsion and steering and to ensure the safety of the vessel.
Starting and connection to the main switchboard of the standby generator is to be preferably within 30 seconds after loss of the electrical power supply but in no case in more than 45 seconds. |
|