During our daily patrolling inspection,the following problems were found :
1,The distance between the butt welding seam and slot is only less than 30mm,it should be more than 50mm in accordance with the Typical structure details approved by class . The designer should give a clear solution to solve this issure ,the stength here shall be analysised and calculated if necessary.
2,The main generation foundation should be fitted after erection when the lower platform is formed an integrity instead of been fitted at pre-erection stage.
3, so far today,let's continue tomorrow |
|